The Hearst Tower
 
 

The Hearst Tower included many unique challenges for both fabrication and erection of the structural steel frame. The “nodes” connecting the diagrid columns pictured to the immediate left were made of 10” plate, milled on all sides to exacting tolerances.

An example of the plate preheating necessary to insure welding quality is shown in the photographs included here. Connections to the diagrid columns and moment connections to the floor beams were fabricated to tighter tolerances than required by the AISC Code of Standard Practice, allowing the diamond-shaped framework to properly support the curtain wall system.

Plumbness and elevation of the diagrid framing was checked every four floors in the field, confirming that Cives Steel Company and Cornell Erectors achieved ± 0” to ½” from theoretical location in all directions.

The challenges of the erector framing the nodes and diagrid columns are readily apparent in these photographs.

 
The diagrid framing started at the 10th floor. It was supported by 42” square “mega columns” and “mega braces,” which provided the majestic open structure from the 3rd to the 10th floors. Installation required two cranes, lifting 100’ long pieces weighing as much as 70 tons. The intersection of the mega braces and mega columns at the 3rd floor required fabrication of “Y” nodes. These nodes were critical to the structure, delivering most of the tower loads to the framing below. Fabricated with 2” and 3” plates, the Y nodes were complex, highly-welded assemblies requiring skilled workmen in the shop to complete. Pictures of the erection of the mega columns, braces, and Y nodes are provided here.
 
 

Hearst Connection Design

In the process of converting this innovative structure from lines on the page to steel in the air, Cives Engineering Corporation faced many challenges.

A safe transfer of the required loads had to be provided for the diagrid system. This involved the analysis of over 15,000 pages of design loads provided to Cives by the Engineer of Record. Tension, compression, shear, and moments, all had to be accommodated in connections that would allow for a safe and quick erection. Despite the vast number of loading conditions, a single “standard” connection configuration was provided at all nodes.

The 77 year old façade also presented many unusual problems. Not only was the newly-erected steel required to interface with existing steel, but it was also, in many instances, required to do so while resisting blast loads that could result from possible terrorist attacks. The most obvious choice would have been to field-weld all of the connections subjected to blast loads. However, this would have represented an unacceptable increased cost to the project, so Cives employed heavy, one-sided connections to resist the inordinately high loads.

The 7th floor skylights represented a different challenge. Instead of battling extremely high loads, the concern was maintaining a clean and aesthetically-pleasing look to the tubular construction. Once again, Cives developed an inventive “concealed-bolt arrangement” that was more cost effective and architecturally desirable than the originally-proposed connection.

These examples represent only a small sampling of the connections required to turn the Hearst Tower dream into reality. Over 500 typical designs were produced as templates for the remaining connections. As with all Cives projects, the requirements of the architect and engineer were coalesced with the strength of the fabricator and erector to produce a structure that was both safe and economical.

.
.
.
 
Northern Division
8 Church Street

Gouverneur, New York 13642

(315) 287-2200

(315) 287-4569 (Fax)

 
Flash Movie - Hearst Tower
   

Modern Steel Construction - July 2006

 
  "A New Angle - A conversation with the steel fabricator of the new Hearst Tower"
 
2006 NASCC Paper
  "New Uses for Old Buildings - The Design and Construction of the 46 Story Hearst Tower in Manhattan, New York"
 
Right Click above then Click Play
   
© 2008 Cives Corporation